The Project
Stadium construction on the new 17,500- seat, $507 million Golden 1 Center—the new home of the NBA’s Sacramento Kings—is complicated. The challenge? Time.
The general contractor, Turner Construction, delivered the LEED Gold-targeted arena in less than two years. There’s also the fact that the arena sits below the water table and the immense scale of the task.
Unfortunately, heavy rains just weeks into the stadium construction project left the excavated jobsite under “… three or four feet of water”, according to Stuart Hunter, Vice President of the waterproofing division of F.D. Thomas, a regional waterproofing contractor.
The stakes were high. The arena was being built below the water table and adjacent to two major river systems. The owner required a fail-safe below grade waterproofing solution. The Golden 1 Center had to operate dry, period.
Once the skies cleared, the pressure was on F.D. Thomas to waterproof 280,000 square feet (26,012 square metres) within 60 days. No excuses, no delays. F.D. Thomas held pre-job meetings to get all the trades dialed-in to support a smooth, efficient installation.
To meet the requirements for operating dry, the contractors used high performance PREPRUFE® Plus waterproofing membrane. Over 96 rolls of PREPRUFE® Plus membrane (30,000 square feet/2787 square metres) were kicked out in a single day. This allowed F.D. Thomas to finish the stadium construction job in 45 days, shattering all expectations.
Only PREPRUFE® Plus waterproofing offers a unique combination of industry-leading features for fast, confident application:
- Rapidly-deployed kick-out rolls
- All-weather seam adhesion with exclusive PREPRUFE® ZIPLAP™ technology
- Permanent lateral water migration resistance from an integrally bonded membrane
- No-waste, release liner-free installation
The Results
Turner Construction officials were ecstatic with the waterproofing and completion results.
The owners especially liked the fact that more than 500 million square feet (4,645,152 square metres) of PREPRUFE® membrane have been installed worldwide on thousands of high-profile, must-not-fail projects. As Hunter says, “It’s the industry workhorse”.
Today the stadium construction project is open to the public and no below grade leaks have been reported in spite of historic El Niño rains and a rising water table. To that, Hunter just grins and says, “Let it rain”.
Blue360sm Total Business Advantage.
The power of GCP products, performance and people.
gcpat.my | For technical information: asia.enq@gcpat.com
GCP Applied Technologies Inc., 2325 Lakeview Parkway, Alpharetta, GA 30009, USA
GCP Applied Technologies (Malaysia) Sdn. Bhd, 7 Lorong CJ 1/1A, Off Jalan Balakong, 43200 Cheras Jaya, Kuala Lumpur, Malaysia
This document is only current as of the last updated date stated below and is valid only for use in Malaysia. It is important that you always refer to the currently available information at the URL below to provide the most current product information at the time of use. Additional literature such as Contractor Manuals, Technical Bulletins, Detail Drawings and detailing recommendations and other relevant documents are also available on www.gcpat.my. Information found on other websites must not be relied upon, as they may not be up-to-date or applicable to the conditions in your location and we do not accept any responsibility for their content. If there are any conflicts or if you need more information, please contact GCP Customer Service.
Last Updated: 2023-09-01
https://gcpat.my/en-gb/about/project-profiles/500-million-stadium-lets-it-rain-new-waterproofing-technology